What code upgrades cost
Typical Florida post-loss upgrades
- Roof decking and fastening (HVHZ zones): +$3-$8K
- Secondary water barrier: +$2-$5K per slope
- Truss tie-downs: +$5-$15K
- Impact windows or shutters: +$15-$40K
- Electrical panel and GFCI: +$3-$10K
- Plumbing backflow / pan: +$2-$5K
- HVAC code requirements: +$2-$8K
Law-and-ordinance coverage tiers
10% of Coverage A (baseline)
- Standard minimum
- Inadequate for HVHZ or major code triggers
25% of Coverage A (upgraded)
- Common intermediate
- Meaningful protection
50% of Coverage A (comprehensive)
- Substantial protection
- Essential for HVHZ properties

How to invoke
- Identify specific code requirement (permit office citation)
- Calculate delta (like-for-like vs. code-compliant)
- Submit as law-and-ordinance line item
- Cite policy endorsement language
Common carrier pushback
- "Like-for-like is sufficient"
- "Code doesn't actually require"
- "Endorsement has sublimit"
- Questioning contractor's code interpretation

Documentation
- Permit office code citation
- Contractor statement on code requirements
- Specific Florida Building Code section
- Cost breakdown (like-for-like vs. code)